10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?

(a) 6 hrs/days

(b) 10 hrs/days

(c) 12 hrs/days

(d) 15 hrs/days

1 Answer

+2 votes
by kratos
 
Best answer

Correct option (a) 6 hrs/days

Explanation:

...