How many men need to be employed to complete the whole job in 5 days, If 15 men can complete 1/3 of the job in 7 days ?
(a) 20
(b) 21
(c) 45
(d) 63
Correct option (d) 63
Explanation:
let ‘N’ no. of men are needed to complete the whole task