A, B and C can do a job in 6 days, 12 days and 15 days respectively. After 1/8 of the work is completed, C leaves the job. Rest of the work is done by A and B together, Time taken to finish the remaning work is:

(a) 35/6 days

(b) 21/4 days

(c) 7/2 days

(d) 15/3 days

1 Answer

+2 votes
by kratos
 
Best answer

Correct option (c) 7/2 days

Explanation:

...