(i) Given 20,000 labour hours = cumulative average
(ii) 90% learning effect
(iii) Rs. 20 per hour
(iv) 8 water tankers
| Units produced | Total output in units | Cumulative average time (unit - hours) | Total hour |
| 1 | 1 | 20000 | 20000 |
| 1 | 2 | 90% of 20000 = 18000 | 36000 |
| 2 | 4 | 90% of 18000 = 16200 | 64,800 |
| 4 | 8 | 90% of 16200 = 14, 580 | 116640 |
Time taken for 8 water tankers =116640 hrs.
Total labour cost = Total no. of hours × per hour 20 116640 × 20 = 2332800