+3 votes
by kratos

11 men can dig 6 3/4 metre long trench in one day. How many men should be employed for digging 27 metre long trench of the same type in one day?

1 Answer

+3 votes
by kratos
 
Best answer

*Let’ consider number of men required be ‘x’ men**

| Length of trench (m) | 27/4 | 27 |
| Number of men | 11 | x |

(27/4)/11 = 27/x

By cross-multiplying

x27/4 = 27(11)

x27/4 = 297

x = (297 × 4)/27

= 44

∴ To dig 27 m long trench of same type in one day requires 44 men.

...